The builders were 27 days late in repairing the Barrandovský bridge Home

According to the deputy, the reason for the delay is, among other things, that there are more fittings in the bridge and they are stronger than expected.

Reconstruction of the bridge began on May 16. Workers first demolished the on-ramp from Strakonická Street, which they are now rebuilding, and milled the roadway and removed ledges, railings and insulation.

The Barrand bridge from 1983 is part of the city ring road and has never been repaired. 140,000 cars cross it daily, which makes it the busiest road in Prague. The reconstruction of the building is spread over several years and will always last only part of the year. In total, the works for all years will cost 594.5 million crowns.